CONSTRUCTION REPORT AUGUST 2020

BLOCK A

Fire Door

  • Fire door & fire shaft door fixing completed in both 6 flat sides & 4 flat side
  • Total No of fire doors-57
  • Total No of Fire Shaft doors-40
  • Total 97 doors Fixing completed

Lift Work

  • L1 lift Frame installation completed,
  • L2 Lift Cabin Installation completed, Door fixing under progress
  • L4 Lift ISMB fixing completed
  • Total 97 doors Fixing completed

UPVC WINDOW

  • 80% UPVC Window Fixing completed

BLOCK WORK

  • Commercial area Block work for Toilet & Duct area Completed.

PLASTERING WORK

  • Plastering work for the 10th floor Connecting bridge parapet wall & Pergola beam Plastering completed.

GRANITE WORK

  • Granite cutting for Sink in Kitchen & Utility area completed.

ELECTRICAL WIRING

  • Completed in 149 flats.

WATERPROOFING WORK

  • Coving work completed in first-floor plantation area and second-floor commercial toilet area.

TOUCHUP WORK

  • 4 flat side External touchup in chhajja completed from 4th floor to 18th floor.

DOOR CLEARANCE

  • Door Jambs correction cutting & Grinding completed for 30nos customer flats.

C BLOCK / Clubhouse

MONTHLY PROGRESS REPORT AUGUST 2020

  • 3rd floor internal plastering for parapet wall in Parking area-1386 sft
  • External plastering in 3rd floor parking area for parapet wall-190 sft