CONSTRUCTION REPORT DECEMBER 2020

BLOCK A

WHAT IS COMPLETED?

  • Tiling work from 18th floor to 12th floor
  • Corridor area flooring from 14th to 7th floor
  • 3rd coat of putty work upto 10th floor
  • Covering firefighting pipeline with POP is from 18th floor to 13th floor
  • Toilet- Wash Basin counter slab fixing from 18th to 14th floor.
  • Fixing of Staircase Railing (S1, S2 & S3) from ground floor to 18th floor.
  • Laying of Granite for Staircase (S1, S2 & S3) from ground floor to 18th floor.
  • Ledge wall top granite fixing from 18th to 14th floor
  • Terrace waterproofing
  • Terrace protective screed work

WHAT IS IN PROGRESS?

  • Lobby area tiling work from 10th floor to 2nd floor.
  • Kitchen L-angle fixing at 18th floor.
  • Corridor plumbing line for drain water purpose
  • Fixing of UPVC window
  • Ledge wall top granite fixing on floor 15th and below
  • Expansion of joints
  • External painting
  • Balcony railing painting

BLOCK B

WHAT IS COMPLETED?

  • 95% plastering work of Terrace area including water tanks
  • Lift (L5) & (L6) water proofing at pit level
  • Granite work from 11th floor to 14th floor
  • Balance primer work of Ramp Area external
  • Terrace level plumbing work
  • Toilet and utility water proofing from 18th floor to 5th floor
  • On all floors firefighting line leakages testing
  • 1st, 2nd and 3rd floor car parking area firefighting line fixing and welding
  • Lift (L8) inside primer work is completed
  • Lift (L8) ISMB channel fixing from 11th floor and below level
  • Lift (L5 and L6) external primer work completed.
  • Ground floor area firefighting line fitting and welding
  • Over head tank inside screed concrete work
  • Lift machine room level and staircase head room level screed concrete work
  • 90% of Primer work at Terrace area
  • Primer work at 1st, 2nd and 3rd floor parapet wall

WHAT IS IN PROGRESS?

  • Terrace area balance 5% of plastering work
  • Skirting is in progress for stair case from 11th floor to 14th floor
  • Balance 10% of Primer work at Terrace area
  • Lift (L5, L6 and L8) Electrical work
  • 1st, 2nd and 3rd floor parapet wall primer work completed, 4th and above is in progress
  • Electrical duct pipe line erection work
  • Corridor rain water pipe line erection work
  • To start staircase handrail work measurement detail taken by fabricator and also fabrication work under progress
  • Terrace level waterproofing work

CLUB LOTUS & MULTI LEVEL CAR PARK AREA

WHAT IS COMPLETED?

  • Wall primer & Plumbing work completed in changing rooms
  • Wall primer completed in GYM
  • External Primer & water proofing work completed of roof top water tanks
  • Lanters -Structures/ Plastering/Primer completed in Lawn area
  • Wall primer completed in Corridor & staircase
  • Vacuum Dewatered Flooring [VDF] completed in GF to 3rd floor Parking area
  • Outer face north & south sides plastering and primer completed
  • Groove cutting & Fire fighting work in progress in GF to 3rd floor Parking area