CONSTRUCTION REPORT FEBUARY 2020

BLOCK A

WHAT IS COMPLETED?

  • Out of 948 windows, 580 numbers of windows fixing completed in 6th series
  • Lift motor room (LMR) staircase completed
  • Terrace floor plumbing line connected to Overhead Water Tank (OHT).
  • Kitchen "L angle" fixing at 18,17,16,15 floor completed in 4th series
  • 3rd coat putty work completed up to 3rd floor.
  • 7th and 6th floor wash basin counter slab fixing completed in 6th series
  • 7th and 6th floor ledge wall top slab fixing completed in 6th series.
  • 253 Toilets completed out of 258 in 6th series.

WHAT IS IN PROGRESS?

  • 90% of first coat of external painting work completed.
  • Fixing of UPVC window
  • Sand paper applying work started at 18th floor.
  • Ground floor main line to panel room conduit work in progress at 6 flat series.
  • 18th to 13th floor corridor tray works in progress at 4 flat series.
  • Ground floor granite flooring in progress.
  • Kitchen counter slab fixing at 18,17,16 floor is in progress.
  • L2 lift cladding work started.
  • L1 lift pit works started.

BLOCK B

WHAT IS COMPLETED?

  • 100% plastering work of terrace area including water tanks
  • Granite work & Skirting is completed for stair case
  • Staircase hand rail work is completed in all the stairs case from ground floor to terrace level
  • Lift (L5, L6 and L8) Electrical work
  • Balance Putty work is completed in L5 staircase
  • Second coat of primer completed in L5, L6, L7 and L8 lifts

WHAT IS IN PROGRESS?

  • Corridor cable tray work under progress for electrical work
  • Electrical duct pipe line erection work under progress
  • Corridor rain water pipe line erection work
  • Handover of firefighting line work is under progress
  • Majority of snag list plastering work and touch up works under progress from ground floor to terrace level
  • At terrace level, main line to sub plumbing line erection work under progress
  • Lift (L5) and (L6) were handover to Otis team and also work under progress
  • Lift (L7) and (L 8) were handover to Mitsubishi team and also work under progress

EXTERNAL WORK

WHAT IS COMPLETED?

  • Entrance gate plastering work completed
  • RCC compound wall completed near north west area

WHAT IS IN PROGRESS?

  • Plastering is in progress near the entrance gate area
  • South side‚Äč external storm water drainage RCC work is in progress
  • Wall cladding work in progress, near the entrance gate elevation
  • External Amenities work is in progress
  • External pitching levelling work is in-progress
  • External driveway area earth work progress for driveway construction purpose
  • Plastering progress for planting box