BLOCK B

What is completed?

    Plastering and masonry

  • U G sump tanks plastering work 100% completed
  • STP area inside plastering work 92% completed
  • Fire shaft, plumbing shaft, communication shafts plastering work completed in 4th flat series and work completed in 6th flat series @ B block & clubhouse
  • @ clubhouses civil works ( 80%) completed
  • Ground floor area Masonry and plastering work completed
  • U G pump room and U G pump room staircase plastering work completed

    Concrete work

  • P C C & concrete for electrical chamber
  • Concrete for a street light foundation
  • PCC for kerbstone work at driveway area
  • Skating board play area 60% completed
  • Skating rink screed concrete completed near B block

    Tiles work

  • Total tile work has been completed in all flat's

    Granite work

  • Ground floor staircase Granite work completed
  • Amphitheater cladding, coping, and nosing work (100%) completed
  • Planter boxes cladding work completed at Clubhouses
  • Cabal stonework (90%) completed at the entrance arch

    Paint and Primer

  • In customer flat's doors and windows jambs putty work completed
  • 4th flat series all flats windows jambs putty work completed

    Lift

  • Lift (L5) and ( L6) work completed ready to move
  • ( L7)Lift & ( L 8) Work completed ready to move
  • Inspection work completed in both the lift
<

    Waterproofing work

  • U G sump tanks waterproofing work completed
  • 4th floor podium area Waterproof work completed
  • STP tanks treatment work 95% completed
  • 5th floor clubhouse waterproofing work started

    Electrical work

  • U g pump room electrical work under process

    Plumbing work

  • along driveway area new plumbing line and inspection chamber work completed except cover

    Scaffolding work

  • Most of the Scaffolding removing work completed

    Garden work

  • Near B Block, north side plain area planting work, near STP pitching area & plain area soil preparation for plantation
  • Opposite to commercial building planting work completed

    External

  • Almost driveway completed except Pavers
  • U G pump room work completed and pump room cleaning work completed
  • Amphitheater surrounding leveling work completed
  • Tennis and basketball play area base preparation work under process
  • Cricket net practice play area civil work Completed
  • Garden maintenance work under process
  • B block South face 100% Drain top concrete completed

    Zen Windows fixed

  • 50% of frames installation work completed

    Shakti Hormann

  • Staircase, fire shafts, electrical and communication shaft doors work completed in 4th flats series & 6th flat series.
  • 90% of frame installation work completed in the clubhouse.

    Clubhouse

  • 4th, 5th, and 6th floor area irrigation work completed for plantation
  • At 4th floor pool area, water leakage testings have been completed yet to start membrane coating
  • Granite cladding work completed for Planter box at 4th, 5th& 6th floor area

What is in progress?

    Material shifting

  • In 6th flat series excess and used materials removing and cleaning work under process

    External

  • Tennis and basketball play area base preparation work under process
  • Garden maintenance work under process

    Electrical work

  • U g pump room electrical work under process

BLOCK A

What is completed?

    Plastering and masonry

  • 6 & 4 flat series, commercial area 100% plastering work completed

    Concrete work

  • All Concrete work completed,

    Granite work

  • All granite works 100% completed
  • Rectification works in progress, Lift flooring Italian marbles fixing work in progress.

    POP work

  • All customer flats touchup work completed
  • All common area touchup work completed

    Painting work

  • All customer flats up to 1st coat emulsion paint completed
  • Commercial area primer work completed
  • All Corridor and staircase up to primer work completed
  • All MS works primer work completed

    Waterproofing work

  • All waterproofing works completed

    Lift

  • L1 & L2 all work completed by Mitsubishi
  • L3 & L4 final installation work in progress 90% completed, load testing work in progress.

    Zen Windows

  • 6 & 4 flat series all flats, common area window fixing completed.

    Spacewood door fixing

  • 6 flat side All flats door fixing work completed, 4 flat side only non-customer flats fixing work in progress up to 40% completed.

    KBS false ceiling

  • 6 flat series all floor corridors false ceiling grid work completed, only tiles fixing work in progress,
  • 4 flat series corridor false ceiling grid work in progress.

    Fabrication

  • Terrace floor all MS works completed

    Louvers fixing

  • 6 & 4 flat series work completed

    Gas pipe

  • 6 & 4 flat series all flats gas pipe and nozzle fixing completed,6 flat side gas meter plate fixing completed, and 4 flats side in progress.

    Broadband work

  • Tatasky broadband work completed at shaft inside 4 & 6 flat series

What is in progress?

    Plastering and masonry

  • Glazing unit modification work in progress.
  • Final finishing and touchup work in progress..

    Concrete work

  • GF open to sky screed concrete work only pending

    Granite work

  • Rectification works in progress, Lift flooring Italian marbles fixing work in progress.

    Tiles work

  • All tiles laying work 100% completed, only damage tile rectification and after door fixing skirting work in progress.

    POP work

  • Non-customer flats after door fixing touchup work in progress 60% flats completed, Undulation touchup work in progress.

    Painting work

  • 6 flat side Non-customer flats 1st coat paintwork completed, 4 flat sides in progress.

    Acid wash & Grouting

  • All customer flats acid wash and grouting work completed, and non-customer flats in progress 30% completed.

    Electrical work

  • 6 flat sides All flats all electrical work completed, 4 flat side only non-customer flats DB dressing work in progress.

    Lift

  • L3 & L4 final installation work in progress 90% completed, load testing work in progress.

    KBS false ceiling

  • 6 flat series all floor corridors false ceiling grid work completed, only tiles fixing work in progress
  • 4 flat series corridor false ceiling grid work in progress.

    Fabrication

  • 4th floor Flats window grill fixing work is ├ąpending.

    Expansion joint work

  • 6 & 4 flats side all expansion joint work completed 95%, only final finishing work in progress.

    Fire fighting

  • All work completed by 95% only final fitting work in progress.