CONSTRUCTION REPORT JANUARY 2020

BLOCK A

WHAT IS COMPLETED?

  • Tiling work from 13th floor to 8th floor
  • Covering fire pipeline from gypsum board, work completed from 14th to 2nd floor in 6 flat series.
  • Covering fire pipeline from gypsum board, work completed from 18th to 5th floor in 4 flat series.
  • "L" angle fixing in kitchen completed from 18th to 6 th floor and 5th to 1st completed without utility.
  • Toilet washbasin counter slab fixing completed from 13th to 9 th floor.
  • Toilet ledge wall top slab granite fixing completed from 13th to 8th floor.
  • Corridor plumbing line for rainwater drain is completed in 6 flat series.
  • Commercial area staircase granite work completed from ground floor to 2nd floor.
  • Balcony railing painting

WHAT IS IN PROGRESS?

  • Lift motor room (LMR) staircase work in progress
  • Terrace floor plumbing line work in progress.
  • Fixing of UPVC window
  • L2,L3 Lift work in progress.
  • Expansion of joints
  • North side elevation external painting work in progress.

BLOCK B

WHAT IS COMPLETED?

  • 98% plastering work of Terrace area including water tanks
  • Terrace level waterproofing
  • Terrace level screed concrete
  • Terrace level plumbing work
  • Electrical work has been completed in all three lifts from pit level to terrace level
  • Granite work is completed including skirting work in each stair case.
  • Putty work is completed in L8 and L 7 staircase
  • Lift (L7) primer work is completed from ground floor to terrace level.
  • In 18 flats flooring tile work is completed
  • In 19 flats utility tile work is completed

WHAT IS IN PROGRESS?

  • Staircase hand rail work under progress in all the stairs case from ground floor to terrace level
  • Electrical duct pipe line erection work under progress
  • Corridor rain water pipe line erection work
  • Lift (L5, L6 and L8) Electrical work
  • Hand over of fire fighting line work is under progress
  • Skirting is in progress for stair case

EXTERNAL WORK

WHAT IS COMPLETED?

  • Entrance gate structural work completed
  • RCC compound wall completed near north west area

WHAT IS IN PROGRESS?

  • Block work and plastering is in progress near entrance gate area
  • South side‚Äč external strom water drainage RCC work is in progress
  • Wall cladding work in progress, near entrance gate elevation
  • External Amenities work is in progress