CONSTRUCTION REPORT JULY 2020

AMPHITHEATRE

ARCH BACKSIDE

BLOCK A - DRAINAGE

BLOCK B - DRAINAGE

EXIT GATE

INTERNAL ROAD

LIFT CLADING

BLOCK A

WHAT IS COMPLETED?

  • Kitchen counter granite slab fixing work completed in the 6th series.
  • Electrical wiring work for 114 flats completed.
  • L2, L3 lift work under progress, L4 lift scaffolding work completed.
  • Tiling work 12 no's of MBR toilet completed.
  • 6 no's of kitchen Dado tile rectification completed.

WHAT IS IN PROGRESS?

  • Fire door fixing is in-progress, total 10 no's fixed.
  • Granite cutting for sink fixing in kitchen and utility is in-progress in 4 flat side
  • Electrical wiring work in stair case 1,2,3 is under progress.
  • Expansion joint cutting work under progress.
  • UPVC window fixing under progress
  • Gas line work under progress for individual flat connection.
  • Touch up work for electrical points for individual flats under progress.

BLOCK B

WHAT IS COMPLETED?

  • Rainwater line packing and plastering work completed .
  • 1st, 2nd, and 3rd-floor level ramp area and parking area with clubhouse masonry work completed .
  • 08 number of flats flooring work completed .
  • 50 number of toilet tile work completed .
  • 35 number of utility work completed .
  • Lift (L5, L6 and L 7) cladding work completed from ground floor to 18th-floor level .
  • Amphitheater cladding, coping and nosing work (85%) completed .
  • 55 number of kitchen counter slab completed .
  • 59 Utility counter slab completed.

WHAT IS IN PROGRESS?

  • L5 and L6 vendor work in progress.
  • Corridor cable tray work under progress for electrical work .
  • Corridor rainwater pipeline erection work.
  • Corridor Handrail packing work under progress.
  • From the ground floor to UG sump, granite cutting work under progress.
  • External painting is in-progress.
  • Basement area electrical work is under progress.
  • Terrace level from mainline to sub plumbing line erection work under progress.
  • Electrical duct pipeline erection work under progress.
  • Backside road work under progress.

EXTERNAL WORK

WHAT IS COMPLETED?

  • Drain work completed in front of A block.
  • Recharge pit 10 nos completed.
  • Clubhouse shuttle badminton court fire fighting work completed.
  • Blockwork on the 3rd floor of the parking area of 1350 sft completed.
  • Blockwork of parapet wall from 2nd floor to 3rd ramp area completed towards A block (330sft).
  • Blockwork of parapet wall from 1st to 2nd floor, 2nd to 3rd floor Ramp area completed towards B block 660 sft.
  • 2nd floor internal plastering work for parapet wall parking area of 1400 sft completed.
  • 3rd floor parking area internal parapet wall plastering work 600 sft completed.

WHAT IS IN PROGRESS?

  • Electrical wiring work in progress.
  • Waterbody work in progress.
  • Road work started from the main gate to B block.
  • Waterbody granite cladding work in progress.
  • Amphitheatre granite cladding work in progress.
  • Fire fighting work of outer ring line is in-progress..