CONSTRUCTION REPORT JUNE 2020

BLOCK A

WHAT IS COMPLETED?

  • Block work for commercial shop area in ground floor is completed
  • 10th-floor parapet wall for a connecting bridge is completed
  • Entrance step block work is completed
  • Plastering work in Entrance step area & commercial shop area is completed

WHAT IS IN PROGRESS?

  • Ground floor granite flooring is in progress.
  • L4 lift work started.
  • L1, L2, and L3 vendor work in progress.
  • Windows lock and handle fixing in progress.
  • Kitchen counter granite slab fixing work in progress in the 6th series.

BLOCK B

WHAT IS COMPLETED?

  • L7 & L8 lift granite cladding work is completed
  • L5 Lift ground floor to 18th floor lift door frame fixing work completed
  • L6 Lift 1st floor to 15th floor door cladding work completed
  • L5 Lift 1st floor to 17th floor level door cladding work completed
  • L5 and L6 lift at entrance pin wall masonry work completed from ground floor to 18th floor level
  • 1st floor to 18th floor level wall cutting work completed near 19th series
  • At 14th-floor level pergola beam concrete completed in north and south faces
  • 1st, 2nd, and 3rd floor level at parking area parapet wall work completed
  • 4th-floor level (4th flat side)  corridor parapet wall work completed
  • Rainwater line packing work completed from 1st to 18th floor 16series
  • Blockwork for parapet wall on 4th floor 4flat side completed
  • Tiling Work in
    • Utility :17 number completed
    • Toilets: 21 numbers completed
    • Ledge wall top:141 numbers completed
    • Washbasin counter:80 numbers completed
    • Kitchen counter slab:12 flats completed
    • Corridor tile  work completed from 18th floor to 10th-floor level (80%)
    • Near amphitheater at north face and east face pitching and planting work completed

WHAT IS IN PROGRESS?

  • L5 and L6 vendor work in progress.
  • Corridor cable tray work under progress for electrical work 
  • Corridor rainwater pipeline erection work
  • Corridor Handrail packing work under progress
  • From the ground floor to UG sump, granite cutting work under progress
  • External painting is in-progress
  • Basement area electrical work is under progress
  • Terrace level from mainline to sub plumbing line erection work under progress
  • Electrical duct pipeline erection work under progress
  • Backside road work under progress

EXTERNAL WORK

WHAT IS COMPLETED?

  • Plantation work is done

WHAT IS IN PROGRESS?

  • Electrical wiring work in progress
  • Water body work in progress.