CONSTRUCTION REPORT APRIL 2020

BLOCK A

WHAT IS COMPLETED?

  • 15th to 18th-floor tiling work completed in 4th series
  • Tiling work completed in 6th series
  • L2 lift cladding work completed in the ground to the 17th floor.
  • 45 No's of Kitchen counter slab fixed at 6 series.
  • 1st to 5th -floor ledge wall top slab fixing completed in 6 series.
  • 1st to 5th -floor wash basin counter slab fixing completed in 6 series.
  • Ground floor mainline to panel room conduit work in progress at 6 flat series.

WHAT IS IN PROGRESS?

  • Ground floor granite flooring is in progress.
  • 90% of the first coat of external painting work completed.
  • 3rd coat putty work completed up to the 3rd floor.
  • Sandpaper applying work started at the 18th floor.
  • Windows lock and handle fixing in progress.
  • L1, L2, and L3 works in progress.

BLOCK B

WHAT IS COMPLETED?

  • 7th-floor elevation concrete work (chejja) is completed
  • Toilets waterproofing work completed
  • Terrace maintenance slab work for overhead tank work completed
  • Handover of firefighting line is completed

WHAT IS IN PROGRESS?

  • From the ground floor to UG sump, granite cutting work under progress
  • External painting work started
  • Lift (L5) and (L6) were handover to Otis team and erection work under progress
  • Lift (L7 )and (L8) were handover to Mitsubishi team and erection work under progress
  • Basement area electrical work is under progress
  • Terrace level from mainline to sub plumbing line erection work under progress
  • Electrical duct pipeline erection work under progress
  • Backside road work under progress
  • East and north side pitching work under progress
  • Corridor cable tray work under progress for electrical work¬†
  • Corridor rainwater pipeline erection work
  • Corridor Handrail packing work under progress

EXTERNAL WORK

WHAT IS COMPLETED?

  • Entrance gate plastering work completed
  • RCC compound wall completed near north west area¬†

WHAT IS IN PROGRESS?

  • Plastering is in progress near the entrance gate area
  • South side, external storm water drainage RCC work is in progress
  • Wall cladding work in progress, near the entrance gate elevation
  • External Amenities work is in progress
  • External pitching levelling work is in-progress
  • External driveway area earth work progress for driveway construction purpose
  • Plastering progress for planting box