CONSTRUCTION REPORT MAY 2020

BLOCK A

WHAT IS COMPLETED?

  • Tiling work completed in 4th series
  • The first coat of exterior painting work is completed.
  • Ledge wall top slab fixing completed in the 4th series.
  • Washbasin counter slab fixing completed in the 4th series.
  • Electrical wiring work completed in the 6th series.
  • Kitchen L angle fixing completed in the 4th & 6th series.
  • Sandpaper applying work completed on the 18th floor.

WHAT IS IN PROGRESS?

  • Ground floor granite flooring is in progress.
  • L4 lift work started.
  • Expansion joint work in progress.
  • L1, L2, and L3 vendor work in progress.
  • Windows lock and handle fixing in progress.
  • Kitchen counter granite slab fixing work in progress in the 6th series.

BLOCK B

WHAT IS COMPLETED?

  • Corridor Tile work completed on 18th to 1st floor in the 4th series.
  • Kitchen dado Tiles work completed in the 10th and 11th floor.
  • Covering of fire pipe with Gypsum board is completed in the 6th series.
  • Kitchen L angle fixing completed in the 4th & 6th series.

WHAT IS IN PROGRESS?

  • L7 lift granite cladding work in progress.
  • L5 and L6 vendor work in progress.
  • Corridor cable tray work under progress for electrical work 
  • Corridor rainwater pipeline erection work
  • Corridor Handrail packing work under progress
  • From the ground floor to UG sump, granite cutting work under progress
  • External painting work started
  • Basement area electrical work is under progress
  • Terrace level from mainline to sub plumbing line erection work under progress
  • Electrical duct pipeline erection work under progress
  • Backside road work under progress

EXTERNAL WORK

WHAT IS COMPLETED?

  • Drainworks completed in roadside
  • Kerb stonework is in progress
  • Plastering is completed near the entrance gate area
  • 1st coat of painting is completed of the entrance gate
  • Elevation design work completed.
  • Roadside elevation granite cladding work completed.
  • Plastering for planting box is completed

WHAT IS IN PROGRESS?

  • Electrical wiring work in progress
  • Water body work in progress.