CONSTRUCTION REPORT NOVEMBER 2020

BLOCK A

WHAT IS COMPLETED?

  • Balcony Flooring tiles completed from 18th floor to 5th floor
  • Vitrified tiles completed from18th floor to 5th floor
  • Lobby area tiling completed for 18th,17th,16th,15th and 1st floor
  • Staircase hand rail completed L2 side
  • Parapet railing completed
  • Stair case granite work completed L1, L2, L3
  • Fire Fighting works completed
  • Terrace water proofing work completed
  • Glass Windows installation completed for flat no. 102

WHAT IS IN PROGRESS?

  • Kitchen L-angle fixing in progress 102
  • Terrace protective screed work in progress
  • Lobby area tiling work in Progress from 10th floor to 2nd floor.

BLOCK B

WHAT IS COMPLETED?

  • Four lift and 3 stair case head plastering work completed
  • Ramp Area Internal and external plastering work completed
  • From 1st floor to 10th floor granite work is completed
  • Connecting bridge Concrete work is completed
  • Lift L7 and L8 waterproofing and concrete work is completed at lift pit level.
  • 8th and 9th floor fire fighting line fixing and welding work , leakages testing work are completed
  • Ramp Area internal and external primer work completed
  • Electrical duct inside and outside primer work ( one coat) completed from 1st floor to terrace level.
  • Lift (L8) ISMB channel fixing work completed up to 10th floor level From terrace level
  • Lift (L5) and (L6) cleaning work completed
  • 16th and 17th floor all flats electrical work completed
  • Shuttering, centring and concrete work of elevation beam is completed
  • In all the floors corridor hand rail fixing work completed

WHAT IS IN PROGRESS?

  • Terrace area 80% of plastering work completed including water tanks. 20% InProgress
  • From 1st floor to 10th floor skirting work is inprogress in each stair case.
  • From 11th floor granite work is Inprogress in each stair case
  • 6th, 7th and 10th floor fire fighting line, leakages testing work in progress
  • 1st, 2nd and 3rd floor car parking area fire fighting line fixing and welding work in progress
  • Connecting bridge primer and paint work completed @ base line
  • Lift (L8) inside primer work in progress
  • Lift (L8) ISMB channel fixing work is in progress from 11th floor and below level
  • From 9th floor and below level angel fixing work in progress
  • Lift(L5) & (L6) water proofing at pit level is inprogress

CLUB LOTUS & MULTI LEVEL CAR PARK AREA

WHAT IS COMPLETED?

  • Walls primer & Plumbing work completed in changing rooms
  • Walls primer completed in GYM
  • External Primer & water proofing work completed of roof top water tanks
  • Lanters -Structures/ Plastering/Primer completed in Lawn area
  • Walls primer completed in Corridor & staircase
  • VDF completed in GF to 3rd floor Parking area
  • Outer face north & south sides plastering and primer completed

WHAT IS IN PROGRESS?

  • Groove cutting & Fire fighting work in progress in GF to 3rd floor Parking area